two men can do a piece of work in 3 day and 6 days respectively. if the work together in how many long will they take if they work together

Answers

Answered by wifilethbridge
20

Answer:

2 days.

Step-by-step explanation:

Work done by first man in 3 days = 1

Work done by that man in 1 day= 1/3

Work done by second man in 6 days = 1

Work done by second man in 1 day= 1/6

Work done by them together in 1 day = 1/3+1/6

                                                             = 3/6 = 1/2

So,1/2  work done by them together in 1 day

So, whole work done by them together  in days = 2 days

Hence it will take 2 days if they do work together.