Two men can do a piece of work in 6 hours and 4 hours respectively. After the first has worked for 2hours, he is joined by the other. By when should the work be completed ?
Answers
Answered by
34
Answer:
3.6 hours = 3 hours 36 minutes
Step-by-step explanation:
Given :
- Two men can do a piece of work in 6 hours and 4 hours respectively.
- After the first has worked for 2hours, he is joined by the other.
To find :
total time taken to complete the work
Solution :
Let A can do the work in 6 hours.
In one hour, work done by A = 1/6
Let B can do the same work in 4 hours.
In one hour, work done by B = 1/4
In one hour, work done by A and B together:
5/12 work is done by both A and B in 1 hour.
A has worked for 2 hours.
Work done by A in 2 hours = 2(1/6) = 1/3
The remaining work = 1 - 1/3
= (3 - 1)/3
= 2/3
A and B together complete the remaining work. Let time taken to complete the remaining work by them together be x hours.
5/12 work is done by both A and B in 1 hour.
2/3 work is done by A and B in x hours.
Total time taken to complete the work = 2 hours + 1.6 hours = 3.6 hours
Similar questions