Two men undertake to do a piece of work for Rs.200. One alone could do it in 6 days, the other In 8 days. With the assistance of a boy they finish it in 3 clays. What is the share of the boy?
Answers
Answered by
5
Answer:
boy = ₹25
Step-by-step explanation:
let the two men be. X & Y
and boy be z
so,
x can do the work in 6 days
y can do the work in 8 days
x+y+z can do the work in 3 days
now let total work be 24 i.e. LCM of 6,8&3
now
efficiency = work/time
so efficiency of
x = 24/6 = 4
y = 24/8 = 3
x+y+z = 24/3 = 8
but
we know efficiency of x is 4 & y is 3
so
efficiency of z = 8 - (4+3) = 8-7 = 1
now
wages of x, y & z = distributed in the ratio of efficiency
so
x = 200 × 4/8 = 800/8 = ₹100
y = 200 × 3/8 = 600/8 = ₹75
z = 200 × 1/8 = 200/8 = ₹25