Varun can coplete a work in 60 days whereas shyam can complete a work in 84 days. in how many they can complete it togrther?
Answers
Answered by
0
Step-by-step explanation:
Varun helps Shyam to complete in 84 days so both complete homework in 84 days
Answered by
3
Answer:
35 days
Step-by-step explanation:
Part of work done by varun in one day = 1/60
Part of work done by shyam in one day = 1/84
Part of work done if both of them work together in one day = (7+5)/420 days
= 12/420=1/35
So, number of days needed to do the work if both of them work together = 35 days
Hope it helps.........
Mark my answer as the brainliest.