English, asked by prajwalgupta0309, 6 months ago


(vii) Standard time is 60 hours and guaranteed time rate is ₹50 per hour. Under Rowan Plan,
what is the amount of wages, if job is completed in 48 hrs.
(a) 2,480 (b) 2,680(c) 2,880 (d) None of the above​

Answers

Answered by sanu15mohd
0

Answer:

2480

Explanation:

I think this is right answer

yesgshshsudjjdbd

Answered by Ishaan038
0

Answer:

The correct option is (d)None of the above

Explanation:

The standard time limit to complete the job is 60 hours. But if the job is completed in 48 hours, with ₹50 per hour payment under the Rowan Plan.

The total amount of wages in 48 hrs will be = '?'

Given:

  • Time taken to complete the job = 48 hrs
  • Per hour charge = ₹50

Therefore,

The amount of wages in 48 hrs will be

 = total \: time \: taken \:  \times  \: per \: unit \: time \: charge

 = 48 \times 50

 = 2400 \: rupees

The total wages of 48 hours of work will be ₹2400.

Therefore, the correct option will be:

(d) None of the above