Math, asked by panchakarlamanjula33, 5 months ago

Vimal can finish a work in 5 days. The same work finished by Vikas
in 3 days. In how many days both of them will finish the work while
working together?​ pls

Answers

Answered by vysh8
4

Answer:

1 day and 11.2 hour

Vimal does ⅕ of work one day

Vikas does ⅓ of work one day

So...

Similar questions