What happens when the spring is cancelled?
Select one
1. The Scrum team disbands immediately
2. The completed spring backlog items are evaluated for a release, and incomplete items are put back into the product backlog.
3. The completed Spring Backlog items are evaluated for a release, and incomplete items are discarded.
4. The complete Sprint backlog is put back to the product backlog.
Answers
Answered by
0
Answer:
2 is correct because it is correct choose it