What three factors are best considered when establishing the sprint length?

Answers

Answered by Shaizakincsem
0
1.    Uncertainty

Uncertainty can come in a variety of forms: Requirements are not well defined; technology is new and potentially risky; an algorithm or interface may be difficult to implement. The list goes on. 


2.    The Amount of Process Required

The amount of process that needs to be accomplished in a sprint will affect sprint length. If implementing code and testing are the only tasks that need to be completed for a user story to be considered complete, shorter sprints are fine. 

3.    Expected Project Duration

The expected project duration may impact the decision for sprint lengths. A short project will benefit from frequent reviews. If a team uses 4-week sprints, a 3-month project will only benefit from three sprint reviews, while a 12-month project will have 13 sprint reviews.