When a project is crashed for a optimum duration 1) direct cost is increased. 2) indirect cost is increased. 3) direct cost is decreased. 4) indirect cost is decreased?

Answers

Answered by rahularyan720
0

Explanation:

determine the optimum cost and time by CPM/PERT network analysis. Project duration can often reduced by assigning more labor to project ... the minimum duration of project with fully crashing in critical path

Answered by syed2020ashaels
0

When a project is crashed for a optimum duration direct cost is increased.

Explanation:

  1. A project is crashed in order to complete the project in the optimum duration with the minimum corresponding cost.
  2. The optimum project duration can be determined as the project duration that results in the least project total cost.
  3. Direct costs are expenses that directly go into producing goods or providing services, while indirect costs are general business expenses that keep you operating.

Hence,

option (1) direct cost is increased is correct.