When data about how much work has been burned down on the team's tasks, is capture across multiple sprints, it gives ?
Select one:
a. natural velocity
b. projected velocity
c. initial velocity
d. estimated velocity
Answers
Answered by
28
Answer:
(D) ESTIMATED VELOCITY
Answered by
5
Answer:
When data about how much work has been burned down on the team's tasks, is capture across multiple sprints, it gives Estimated velocity.
Explanation:
Estimated velocity is used to estimate how much work can a team achieve per sprint. Not only that, it also helps to estimate how long will a project take to be reach a certain level of growth.