Which documents all change request to baselined items?

Answers

Answered by Bhavya34567890
0
Change control register documents all change request to baselines items.
Answered by gratefuljarette
0

Change Register documents all change request to baselined items.

Explanation:

  • Change Register is also called the change log. It gives a central place for storing all the related information and change in the project. All the project change at a specific point. If the change you need to record the information and relating to change.
  • It helps to monitor as well as control the effect of that change on the project. It is an asset of any project. It provides the project manager with a single source of information relating to all project change.

Learn more about Change Register

An astronaut registers change in his body in terms of

https://brainly.in/question/3708091

Write an application for the change of phone number in school

https://brainly.in/question/5628174

Similar questions