Which of these following best represent the scrum approach to planning?
a. planning is a continuous activity done jointly by the scrum master and product owner
b. detailed planning is done up front and not revisited
c. the whole team together does just enough upfront planning followed by continuous planning throughout the project
d. Only planning in scrum is the Sprint Planning
e. Daily Scrum is one of the planning events
Answers
Answered by
26
C. The whole team together does just enough upfront planning followed by continuous planning throughout the project
Explanation:
- Scrum is a project management framework in which the project is subdivided into smaller tasks and they are placed on a list called backlog.
- If any project from the list needs to be completed, it is taken from the list and given to team who can get it done in limited time frame. This time frame is called sprint.
- History of this technique goes back to 1986 when two Japanese men used it as a more efficient way for product development. Nowadays it is used in software development.
- The process starts with what can be known or seen and then the progress is tracked and tweaked as per the need. Transparency, adaptation and inspection are three pillars of this technique.
- Communication is an important part of the process and is carried out regularly though meetings.
Learn More:
Difference between Java and Javascript
https://brainly.in/question/15296051
Answered by
7
only planning in scrum is the Sprint planning