 \sf{12  \: workers \:  can  \: complete \:  a \:  piece \:  of  \: work \:  in \: 10  \: days}

 \sf \frac{1}{3} rd \:  of \:  original \:  No's  \: of  \: workers

 \sf{ \implies{12 \times  \frac{1}{3}  = 4 \:  \:  \: workers}}

No of workers reduced then more no days are required

 \sf{12 \times 10 \div 4 = 30}

 \sf{ \orange{ \star \: {Ans = 30 days}}}

 \sf{ \bold{ \blue{hence \:  20 \:  days  \: more}}}