work uncertified is valued at ____
a. market price
b. cost
c. cost or market price, whichever is less
d. cost or market price, whichever is higher
Answers
Answered by
22
Answer:
Work certified is valued at contract price (i.e , selling price), and includes an element of profit. Work Uncertified. This is that part of the work-in-progress which is not approved by the architect or engineer. This is valued at cost and thus does not include an element of profit.
Answered by
0
We need to answer that the work uncertified is valued at what rate
- Work uncertified is calculated at cost
- The correct option is B
- Work certified is work that has been completed and approved and is hence calculated at the contract price and some profit may be added to it
- Work uncertified can be defined as work in progress or work not yet completed or approved.
- Work that has not received approval from the contractor or engineer is also known as work uncertified.
- In such cases, the work is calculated at cost and no profit amount is added
- However, some retention money may be kept by the employer
Similar questions