Math, asked by ExToRJiT, 1 year ago

Working 5 hours daily, Shaheed can embroider
3 sarees in 21 days.How many days will it take for him to embroider 6 sarees working 7 hours daily?

Answers

Answered by sachin238
1
36 it will the answer I hope it is right

Nishant05: Then we will divide it by the no. of sarees to find the time taken to produce one saree
Nishant05: 21×5÷3=35
ExToRJiT: now
Nishant05: Then we will multiply the time taken for one saree with the total no. of saree
Nishant05: Then we will divide it by total working hours in a day
Nishant05: 35×6÷7=30
ExToRJiT: yes its right
ExToRJiT: thnx
Nishant05: solved
Nishant05: Welcome
Answered by Nishant05
1
I think it will be 30