X and Y can do a piece of work in 10 days and 6 days respectively.they work together for 2 days and Y leaves the work.In how many days X will finish the remaining work.
Answers
Answered by
1
Step-by-step explanation:
Number of days X and y does his work
10+6
=16
Number of days Y leaves from work=16-2= 14
So,he finished his work in 14 days