X and y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days y joined him till the completion of work. How long did the work last?
Answers
Answered by
3
Answer:
10 days
Step-by-step explanation:
Work done by X in 4 days = 1 x 4 = 1 .
20 5
Remaining work = 1 - 1 = 4 .
5 5
(X + Y)'s 1 day's work = 1 + 1 = 8 = 2 .
20 12 60 15
Now, 2 work is done by X and Y in 1 day.
15
So, 4 work will be done by X and Y in 15 x 4 = 6 days.
5 2 5
Hence, total time taken = (6 + 4) days = 10 days
Answered by
2
Answer:
6 days
x 20 dys
y 12 days
then lcm of 12 n 20 is 60
so x in 3
y in 5
total in 8
total wrk is 60
x wrks 4 days i.e 3*4=12
60-12=48
then y join
now 3+5=8
rmng wrk 48
divded by 8 so we found tht 6 dys
Similar questions