X and y can do a piece of work in 20 days and 12 days respectively. X started the work alone and then after 4 days .Y joined him till the completion of the work. How long did the work last? Select one: a. 10 days b. 6 days c. 20 days d. 15 days
Answers
Answered by
5
b. 6 days
Per day's work of x is 1/20
And per day's work of y is 1/12 days
So work done by x in first 4 days
= 1/20×4= 1/5
So the remaining work be
1-1/5=4/5
now work done by x and y together = 1/20 + 1/12
=2/15
So the remaining work be done by both x and y
= 2/15 ×D = 4/5
So D = 4/5×15/2 =3×2 = 6
Therefore for 6 days they worked till last
HOPE IT HELPS YOU ☺☺ !!