Math, asked by anjalijoshi4242, 1 year ago

X and y together can completework in 12 days if y work only for half a day daily then how many days x and y together completethe work

Answers

Answered by Anonymous
0

A and B together can complete the piece of work in one day=1/12

A can complete the piece of work in one day=1/20

B can alone complete the piece of work in one day=1/12–1/20

LCM(12,20)=60

=>(5–3)/60=2/60=1/30

Therefore days require to complete the work=1÷1/30=1×30=30days

hope this answer helpful u