x can do 3/4 of the work in a 12 days. in how many days can he complete 1/8 of the work?
Answers
Answered by
42
let the total work = y
so , we can say =
3/4×y = 12days
y. = 16
so, now days required to do 1/8 of y
=. 1/8y =1/8×16 = 2 days ans.....
⚡hope it helps you ⚡
so , we can say =
3/4×y = 12days
y. = 16
so, now days required to do 1/8 of y
=. 1/8y =1/8×16 = 2 days ans.....
⚡hope it helps you ⚡
Answered by
43
☜☆☞
hope it helps u.
☜☆☞
hope it helps u.
☜☆☞