X Y and Z together can do a piece of work in 4 days. If X and Y can do the work in
5 days. Y and Z in 10 days, find the number of days in which X and Z. while working
together, will be able to finish the work.
Answers
Answer:
x and z can finish the work in 5 days
Step-by-step explanation:
=)(x+y+z)'s 1 day work=1/4
=)z's 1 day work=(x+y+z)'s 1 day work - (x+y)'s 1 day work
=(1/4)-(1/5)
=(5-4)/20 [By taking L.C.M]
=1/20
=)x's 1 day work=(x+y+z)'s 1 day work-(y+z)'s 1 day work
=(1/4)-(1/10)
=(5-2)/20 [By taking L.C.M]
=3/20
=)(x+z)'s 1 day work=(3/20)+(1/20)
=4/20
=1/5 [By dividing both denominator and numerator by 4]
=)So,(x+z) can finish the work together in 5 days.
Time taken by X, Y and Z to complete a piece of work= 4 days (given)
Time taken by X and Y to complete the work together= 5 days (given)
Time taken by Y and Z to complete the work together= 10 days (given)
X's one day work= (X+Y+Z)'s 1 day's work - (Y+Z)'s 1 day's work
=> 1/4- 1/10
LCM of 4 and 10= 20
1/4×5/5= 5/20
1/10×2/2=2/20
5/20-2/20= 3/20
X's one day work= 3/20
Z's one day work= (X+Y+Z)'s 1 day's work - (X+Y)'s 1 day's work
=> 1/4-1/5
LCM of 4 and 5= 20
1/4×5/5= 5/20
1/5×4/4= 4/20
5/20-4/20=1/20
Z's one day work= 1/20
Time taken by X and Z to complete the work together= 3/20+1/20
=> 4/20
Reciprocal of 4/20= 20/4
20/4=5
Thus, the time taken by X and Z to complete the work together is 5 days.
HOPE IT WAS HELPFUL.
PLEASE MARK MY ANSWER AS BRAINLIEST..