You work in a manufacturing organization. Consider an equipment that is available for production
for 18 hours per day. On a regular day, 350 items are processed through this equipment, each of
which takes around 25 minutes on it. Total time required for setting up the equipment is 15
minute, 1 minute is required to obtain the final product Out of the items that are processed through
the equipment, 20% requires rework and needs to undergo the set-up and processing time once
again. In rest of the time, the equipment remaitis idle. What is the total waste time in minutes?
(A) 30
(B) 175
(C) 630
(D) 205​

Answers

Answered by ramesh015
4

Answer:

(C) 630 your answer to the question