1. Your developer has provided u with an estimate based on the “cost per line of code".
What type of estimate did the developer use to provide this information?
A. Parametric estimating.
B. Bottom-up- estimating.
C. Analogues estimating.
D. PERTestmating .
Answers
Answered by
1
Answer:
the correct answer is option c
analogues estimating