10 men can finish a piece of work in 10 days whereas it takes 12 women to finish it in 10 days. if 15 men and 6 women undertake to complete the work, how many days will they take to complete the work?
Answers
Answered by
41
............................
Attachments:
Answered by
12
Answer:
If 15 men and 6 women started to finish up the same work, it will take 5 days for them to complete it.
Solution:
Given, 10 men can finish up the work in = 10 days
12 women can finish up the work in = 10 days.
Thus, Work of 10 men = Work of 12 women
10 men = 12 women
5 men = 6 women
∴ 15 men and 6 women = 15 men + 5 men = 20 men.
Thus, time required by 15 men and 6 women = time required by 20 men
10 men needs = 10 days
And, 20 men needs
= (10 × 10)/20 days
= 5 days.
Hence, if 15 men and 6 women started to finish up the same work, it will take 5 days for them to complete it.
Similar questions
Economy,
8 months ago
World Languages,
8 months ago
Math,
8 months ago
Math,
1 year ago
Social Sciences,
1 year ago
Science,
1 year ago
Science,
1 year ago
Science,
1 year ago