10 men cut 15 trees in 2 hours how many trees can be cut by 8 people in 3 hours
Answers
Answered by
2
Answer:
18 Tress
Step-by-step explanation:
15 trees cut in 10* 2 = 20 man hrs
8 people 3 hrs = 8*3 = 24 man hrs
20 man hrs required for = 15 tree
1 man hr required for = 15/20
24 man hrs required for = (15/20)*24 = 18 Trees