10 people can do a piece of work in 15 days. how many people can complete the same work in 10 days.
Answers
Answered by
2
Answer:
10 persons can finish work = 15 days. Therefore, 1 person can do = 15 × 10 = 150 days. 25 persons can do = 150/25 = 6 days.
If you like my answer, please mark it as ✔️BRAINLIEST! Good Luck and have a nice day!! :)
Answered by
0
Answer:
15 people
Step-by-step explanation:
for 15 days .. 10 people
for 1 day .. 15/10
for 10 days.... 15/10×10
=15 people