10 women can do a piece of work in 20 days. If 2 of the women deny to work, then how many days are required to complete the work?
Answers
Answered by
10
10 women can do a piece of work in 20 days.
so, 1 woman can do a piece of work in 10 × 20 = 200 days.
A/C to question,
now, 8 woman have to do same work.
so, use formula
10 × 20 = 8 × D
D = 200/8 = 25 days
hence, 25 days are required to complete the work.
so, 1 woman can do a piece of work in 10 × 20 = 200 days.
A/C to question,
now, 8 woman have to do same work.
so, use formula
10 × 20 = 8 × D
D = 200/8 = 25 days
hence, 25 days are required to complete the work.
Answered by
10
Hey there !
10 women can complete a work in 20 days
In one day , 10 women can complete 1/20 th part of work
now ,
1 women can complete 1/200 part of work each day
Given in the question ; 2 of the women denied to work .
Remaining women = 10 - 2 = 8
Each day , 8 women can complete 8/200 = 1/25
required part of work to be done = 1
So working for 25 days , They can complete work . ( each day 8 women can complete 1/25 of work)
Therefore , A work which can be completed in 20 days by 10 women can be done in 25 days if 2 women denies to work .
Similar questions