100 PEOPLE CAN CONSTRUCT A BRIDGE IN 30 DAYS.HOW MANY MORE PEOPLE NEED TO BE EMPLOYED IF THE BRIDGE NEEDS TO BE COMPLETED IN 24 DAYS?

Answers

Answered by Shaanraj
3
Hey mate!!!

 <b >Here is your answer ;</b >


Given,
It takes 30 days to construct a bridge by 100 people

Then,
It takes 1 day to construct a bridge by (30 * 100 )people
[inversely proportionality]


Thus,

It takes 24 days to construct a bridge by
 \frac{(30 * 100)} {24}

= 125 people.