38. A contractor who fails to complete a building in a certain specified time is compelled to
forfeit Rs. 200 for the first day of extra time required and thereafter forfeited amount
is increased by Rs. 25 for every day. If he loses Rs. 9,450, for how many days did he over-
run the contract time?
945o = 2 ( 2 (125) + (0-1) es
a) 19 days
c) 23 days
b) 21 days
d) 25 days.
Answers
Answered by
2
pls follow me and mark me as brainlist
Answered by
1
Step-by-step explanation:
Here is the right answer