12 man build a wall in 14 days. One man does the work of 2 women . if 8 men and 4 women are employed how long will it take to build the wall
Answers
Answered by
1
Answer:
16 4/5
Step-by-step explanation:
12 men can build a wall in 14 days
8 men can build a wall in 21 days
2 women=1 man
4 women=2 men
then,
2 men can build a wall in 84 days
there fore 1/24+1/84=5/84 =84/5=>16 4/5