12 men can complete a work in 18 days.6 days after they had started working, 4 men joined them. How many days will all of them take to complete the remaining work?
Answers
Answered by
46
Assume 1 man does 1 unit of work in 1 day.
Then total work = 12×18=216 units
In initial 6 days, 12 men worked.
Work completed = 12×6=72 units
Remaining work = 216 - 72 = 144 units
Then 16 men work
Time required for them to finish the job =14416=9=14416=9 days
Then total work = 12×18=216 units
In initial 6 days, 12 men worked.
Work completed = 12×6=72 units
Remaining work = 216 - 72 = 144 units
Then 16 men work
Time required for them to finish the job =14416=9=14416=9 days
Answered by
20
Assume 1 man does 1 unit of work in one day.
Then total work = 12 × 18 = 216 units
In initial 6 days, 12 men worked.
Work completed = 12 × 6 = 72 units
Remaining work = 216 - 72 = 144 units
Then 16 men work
Time required for them to finish the job = 14416 = 9 days