Math, asked by vinitjain1924, 1 year ago

15 members complete work in 12days how many more needed to complete in 9days

Answers

Answered by Abhishekraj111
1
let total no. men ..x
so, 15×12=x×9
x=20
more men required=20-15=5
so ans=5