2 can do a piece of work in 3 days and 6 days respectively if they work together in how many days will they finish the work

Answers

Answered by intelligentkido
2
If A completes work in 3 days and B completes the same work in 6 days

A's one day work = 1/3 day
B's one day work = 1/6 day

A's and B's one day work together = 1/3+1/6
= 1/2

Therefore total number of days required would be 2 if they work together
Answered by gurdhyan98
1
they both will finish work in 2days