Math, asked by rk11111, 1 year ago

3
Merry can do a painting job in 20 days while Jerry can do the same job in 30 days. How long will they take
to complete the work if they work together?​

Answers

Answered by sagar9122
0

Answer:

no. of days they take to complete the work together=LCM(20,30)

=60

hence, they complete the work in 60 days

Answered by arnabtherockstar
2

Answer:

12days

Step-by-step explanation:

Merry can do 1 work in = 20 days

in 1 day she could do= 1

20

Jerry can do 1 work in=30 days

in 1 day she could do= 1

30

in 1 day they both can do-

1 + 1

20 30

2+3

60

5

60

so to complete 1 work

1 / 5

60

60

5

12 days

please mark me as brainliest