30 men can finish the work in 16 days. How many days will 40 men finish the same work ?
Answers
Answered by
16
The ans..is 24 ...
For explanation look at the attached one...
Attachments:
Answered by
1
Answer:
If 30 men can finish a work in 40 days then 40 men can finish the work in 30 days.
Men × days = men1 × days1
30 × 40 = 40 × x
x = 30 days
Step-by-step explanation:
I HOPE THIS MAY HELP YOU......