Math, asked by dutchm123, 9 months ago

36 men can complete a piece of work in 20 days in how many days will the work be done if the number of men is reduced to 12

Answers

Answered by vikhyat04
1

Answer:

Step-by-step explanation:

1/36    ---->      1/20

1/12 -------> ?

(1/12 *1/20) / 1/36

3/20

Answered by Anonymous
8

Answer:

Let the no of days required be x

x=36×20/12=60 days

60 days will be required

Similar questions