4 men and 6 boys can finish the work in 5 days while 3 men and 4 boys can finish it in 7 days.find the time taken by 1 man alone or that by 1 boy alone
Answers
Answered by
1
Answer:
HI mate.....
your answer is 10/7
Step-by-step explanation:
mens days
4. 5.
3. 7.
so, it is inverse variation.
boys days
6. 5.
4. 7.
so, it is also inverse variation.
now, to find the number of days taken for 4,3 mens and 6,4 boys to finish the work
=inverse variation
=4/3*6/4
=2.
number of days =2
so, for 1 man or boy,
=5/7 /2
5/7*2/1
=10/7.
so, 1 man or boy will be taking 10/7 days to finish the work.