40 men can complete a work in 40 days. they started the work together. but at the end of each 10th day, 5 men left the job. the work would have been completed in how many days

Answers

Answered by king180
2
40 men complete a work in40 days ,5men left the job then the work would have been completed in 45 days
Answered by sankar007
8

Let a man can do 1 unit/ day.

Total work = 40men×40days

= 1600 units

40 men can do the work in 10 days

= 400 units

According to question,

(5men left after 10 days)

35 men can do the work in 10 days

=350 units

30 men can do tlhe work in 10 days

=300

25 men can do the work in 10 days

=250

20 men can do the work in 10 days

=200

men left 20−5=15 and

work left = 1600−1500=100 units

they will complete in 100/15=6 2/3days

Total days =50+6 2/3=56 2/3 days