45 men can complete a piece of work in 16 days .4days more 36mens joined them how many days will they take to complete the remaining work?

Answers

Answered by nandani86
0
45 men complete the work in 16 days. they worked 6 days. 
Therefore, the remaining work will be completed by 45 men in (16-6)days.
30 men joined the camp 
therefore total number of men=75 (45+30).
45 men can complete the remaining work in 10 days.
1 man can complete the remaining work in 10*45 days
75 men can complete the work in = {(10*45)/75}days
450/75
6 days
hope it helps you