Math, asked by ranveer24524gmail, 1 year ago

5% complete a certain job in 2 days how many days will 10 persons take to finish the job

Answers

Answered by HappiestWriter012
1
Question :- 5 person complete a certain job in 2 days how many days will 10 persons take to finish the job


Numbers of persons ∝ 1/ Time taken to
complete

If number of persons double, time will be halved.

Here, 5 persons -----> 2 days.

10 persons -----> x days.

We know that x ∝1/y => x1 * y1 = x2 * y2

5*2 =10* x

x = 1 day.

Hence, 10 persons take 1 day.