50 labourers can dig a pond in 16
days, how many labourers will be
required to dig another pond,
double in size, in 20 days?
Answers
Answered by
2
Answer:
80 labourers
Step-by-step explanation:
if the size is doubled ,let 100 labourers dig the first pond in 16 days
let no. of labourers be x
100=16
20=x
100*16
ans/20
1600/20=80
Answered by
1
Answer:80 labourers
Step-by-step explanation:
2×(M1×D1)=M2×D2
2×50×16=M2×20
M2=80