Math, asked by arshiahmadknp, 8 months ago

50m long wall can be painted in 16days how many days will be required to paint 87.5m long wall​

Answers

Answered by twinklesingh95
2

Answer:

approx 25.39 days

Step-by-step explanation:

wall can be painted in 1 day = 50/16 = 3.125m

days required to paint wall = 3.125 mutiply by 87.5m = 25.39 days