56 men can do a work in 8 day's. How many men can do a work in 7 days?
Answers
Answered by
2
it is indirect speech
56*8=x*7
448=7x
7x=448
x=448/7
x=64 men
56*8=x*7
448=7x
7x=448
x=448/7
x=64 men