6 men can do a piece of work in 12 days while 8 women can do the same work in 18 days. The
same work can be done by 18 children in 10 days. 4 men, 12 women and 20 children work
together for 2 days. If only men have to complete remaining work in 1 day, then find the
required number of men
Answers
Answered by
1
Answer:
36 Men will be required to complete remaining work in 1 day
Step-by-step explanation:
6 men can complete a piece of work in 12 days
= work = 6×12 = 72 men days
1 Man 1 day work = 1/72
8 women can complete the same piece of work in 18 days
= works = 8×18 = 144 Women days
1 women 1 day work = 1/144
18 children can complete the same piece of work in 10 days.
= work = 18×10 = 180 children days
4 men, 12 women and 20 children work together for 2 days.
Work done = 2(4×1/72+12×1/144+20×1/180)
= 2(1/8+1/12+1/9)
= 2(2+3+4)36
= 18/36
= 1/2
Remaining work = 1-1/2 = 1/2
1 Man 1 day work = 1/72
Number of men required to complete remaining work in 1 days = (1/2)/(1/72) = 36
36 Men will be required to complete remaining work in 1 day.
Answered by
0
Answer:
ok please mark me brainlist and follow me
Attachments:
Similar questions
English,
2 months ago
Computer Science,
2 months ago
Social Sciences,
2 months ago
Physics,
5 months ago
English,
10 months ago
Math,
10 months ago
Math,
10 months ago