72 men can build a wall 280 m long in 42 days.The number of persons who would take 36 days to build a similar wall of length 100m will be?
Answers
Answer:
M2=30
Step-by-step explanation:
We know that: m1d1h1/w1=m2d2h2/w2
h1=h2 (as they are doing the work in same number of hours per day)
m1d1/w1=m2d2/w2
72×42/280=m2×36/100
84/280=m2/100
8400=280m2
m2=30
30 members will do the work
Let us make a mathematical problem with the help of the given quantities:
We assume:
- Number of men = M
- Length of wall = L
- Time in days = D
M L D
72 280 42
? 100 36
Here, M is directly proportional to L as if number of men increases, the length of building a wall will increase.
Also, M is inversely proportional to D as if number of men increases, number of people required to complete a work will decrease.
∴ the required number of men
= 72 * 100/280 * 42/36
= 30
∴ 30 men would take 36 days to build a wall of length 100 m.