8 man do work in 9days .how many days 6 men take to do this work

Answers

Answered by MarkAsBrainliest
3
Answer :

8 men do a work in 9 days

1 man do the work in (8 × 9) = 72 days

6 men will do the work in (72/6) = 12 days

∴ in 12 days, 6 men will do the work.

#MarkAsBrainliest
Answered by HimanshuKumarPal
0
Let the day required to do the work be x
no . of men 8 6
no.of days. 9 x
It is in inverse variation
so,8×9=6×X
72=6X
x=72/6
X=12