Math, asked by drthdate8060, 1 year ago

A alone can finish a piece of work in 12 days and B alone can do it in 15 days if both of them work at it together how much time will it take to finish it

Answers

Answered by AnshPasi
6

Answer:

6.6 days

This is very easy just take the reciprocal of work as work done in 1 days

Attachments:
Answered by rakhister80
8

Answer:

Both can finish the work in 6  \frac{2}{3}

days

Step-by-step explanation:

Time taken by A to finish the work = 12 days

Time taken by B to finish the work = 15 days

Work done by A in 1 day = ½

Work done by B in 1 day = 1/15

Work done by (A+B) in 1 day = ( \frac{1}{12}  +  \frac{1}{15} ) =  \frac{9}{30}  =  \frac{3}{20}

Time taken by (A + B) to finish the work  \frac{20}{3} days, i.e., 6 \frac{2}{3} days.

Hence, both can finish the work in

6 \frac{2}{3} days.