A & B can do a piece of work in 60 & 75
days respectively. Both begin together,
but after certain days A leaves off. In
such a case B finishes the remaining
work in 30days. After how many days
leaves off?
Answers
Answered by
165
Gɪᴠᴇɴ :-
- A & B can do a piece of work in 60 & 75
- days respectively.
- Both begin together, but after certain days A leaves off.
- In such a case B finishes the remaining work in 30days.
Tᴏ Fɪɴᴅ :-
- After how many days A leaves off ?
Sᴏʟᴜᴛɪᴏɴ :-
LCM of 60 & 75 = 300 unit = Let Total work.
So,
→ Efficiency of A = (Total work) / (Total No. of Days.) = (300/60) = 5 units/day.
Similarly,
→ Efficiency of B = (Total work) / (Total No. of Days.) = (300/75) = 4 units/day.
Now, we have given that, Both begin together,
Both begin together,but after certain days A leaves off and, B finishes the remaining work in 30days.
So,
→ in Last 30 days B alone did = 30 * 4 = 120 units of work.
Therefore, we can say that, rest amount of work was done by both (A + B) before A left.
So,
→ Left work = 300 - 120 = 180 units
And,
→ Time taken by (A + B) Now = (Left work) / (Efficiency of Both) = 180 / (5 + 4) = 180/ 9 = 20 days. (Ans.)
Hence, A leaves off after 20 days.
Answered by
352
▪ A and B can do a piece of work in 60 and 75 days respectively. Both begin together but after certain days A leaves off . In such a case B finishes the remaining work in 30 days. After how many days A leaves off?
then, let the total work be the L.C.M. of 60 and 75 i.e.,
NOW,
▪ It's given in the question that both, A and B started the work together , but after certain days A leaves off
and B finishes the remaining work in 30 days
➡ that means B worked alone for the last 30 days
Then, it can be said that the remaining amount of work was done by (A+B) together , before A left.....
Then,
▪ therefore,
thus,
Similar questions