Math, asked by dishitapa8199, 1 year ago

A and b can complete a work alone in ,18 days and 24 days respectively.if b started work alone and after 3 days a also joined then in how many days whole world will be completed.

Answers

Answered by brajmohank94
0

Let A work for x days

In x days , work by A = x/18 work

Time given by B = x + 3 days

In x +3 days, work by B = x+3/24 work

x/18 + x+3/24= 1

7x + 9/72 = 1

7x + 9 = 72

]7x = 72 - 9 = 63

x = 63/7 = 9 days

Time taken to complete work = 9 + 3 = 12 days