Math, asked by Shivamd9794, 1 year ago

A and b can complete a work in 8 days working together. b alone can do it in 12 days after working for four days, b left the work how many days will a take to complete the remaining work?

Answers

Answered by RvChaudharY50
0

Given :-

  • A and B can complete a work in 8 days working together.
  • B alone can do it in 12 days ..
  • After working for four days, B left the work .

To Find :-

  • How many days will a take to complete the remaining work ?

Solution :-

LCM of 8 & 12 = 24 unit = Let Total work.

So,

→ Efficiency of (A + B) = (Total work) / (Total No. of Days.) = (24/8) = 3 units/day.

Similarly,

→ Efficiency of B = (Total work) / (Total No. of Days.) = (24/12) = 2 units/day.

Hence,

Efficiency of A = Efficiency of (A + B) - Efficiency of B = 3 - 2 = 1 unit/day.

Now, it has been said that, both work together for four days.

So,

in 4 days both (A + B) completes = Efficiency of (A + B) * No. of Days. = 3 * 4 = 12 units .

Than,

work left to be done = 24 - 12 = 12 units.

Now, we have given that, B left the work. Therefore, we can say that, rest 12 unit of work was done by A alone.

Hence,

Remaining work = 12 units.

→ Efficiency of A = 1 unit/day.

→ Time taken by A = (Remaining work) / (Efficiency of A) = (12/1) = 12 days. (Ans.)

A complete the remaining work in 12 days.